THE PROJECT
The new build medical centre is a part single-story and part two-story structure. Internally the centre houses 15 consultation rooms, staff and admin rooms, reception, storage, WC and disabled facilities.
The structure is steel frame with traditional masonry and insulation. There are 3 types of cladding: brick facing elevations, off white render, and cedar cladding with aluminium windows throughout.
Externally the site includes a large car park with rain water drainage throughout.
The project achieved BREEAM Excellent.
Challenges & Solutions
Local school
The site was located directly opposite an operational school. Our entrance to the site was also opposite to the school’s entrance on a main road.
Our Project Manager managed a stream of frequent communication with the school and local residential housing estate. He set up a facebook page containing a live stream of updates which was received extremely positively.
A notice board was utilised opposite the school to display updates and notifications.
£1.7M
CONTRACT VALUE
44 WEEKS
CONTRACT DURATION
Customer
Westrop Surgery
Architect
Osmond Tricks
Quantity Surveyor
Burke Hunter Adams
Form of Contract
Single Stage